Waste Water Treatment Plant
Installing Micropiles, Rock Anchors
The city of Bowling Green, Kentucky, acquired Federal Stimulus money to construct a new, multi-million dollar Wastewater Treatment Facility to replace the outdated facility.
Due to the many fissures and caves in the area, the Engineer of Record required the facility to be supported and tied down.
Micropiles and Rock Anchors were installed to support and tie down all buildings in this state-of-the art Wastewater Treatment Plant.
The results were fantastic. We installed over 30,000 lineal feet of Micropiles and Rock Anchors. We fulfilled the requirements of the Engineer of Record and general contractor.
CNC Foundations was required to test 10% of the Micropiles installed. During the testing, we met and exceeded the requirements for total movement allowed by the Engineer of Record. The worst movement during the testing was 2,000th of an inch (the requirement was for no more than ½” movement).
CNC Foundations more than exceeded the requirements of the EOR and the Owner.
SECTOR
Municipal Utilities, Waste Water Treatment Plant
LOCATION
Bowling Green, Kentucky
APPLICATION(S)
Micropiles, Rock Anchors
St. Louis Ballpark Village Site – Installing Vibratory Stone Columns
Ballpark Village St. Louis, Clark Avenue, St. Louis, MO, USA
View Case Study
Vibratory Stone Column Uplift Anchor Installation at Western Carolina University
Cullowhee, NC
View Case Study
Pre-Drill VSCs and VCCs Fitness Center Chicago Suburb Oak Brook
OakBrook, IL
View Case Study
8259 Bunkum Rd
Caseyville, IL 62232
Atlanta | Chicago | Columbus | Des Moines | Indianapolis | Raleigh | St. Louis | Memphis | Newark
CNC Foundations builds value into your construction project. We employ a full-time engineering staff and support personnel who enable us to meet the most challenging demands of construction projects, including design and installation.