Pharmaceutical Manufacturing Plant

Installing Vibratory Stone Columns

Ground Improvement- Installing Vibratory Stone Columns

PROJECT OVERVIEW

A chemical plant was adding a new manufacturing facility. The sub-surface conditions generally consisted of a sand/gravel material to a depth of approximately 10 feet. The material below the fill consisted of stiff gray clay approximately 9 to 18 feet thick.

REQUIREMENTS AND CHALLENGES

The design requirements for this new facility included columns and continuous footings with a bearing pressure of 1300 psf and the floor slab was 230 psf. The maximum long-term settlement was less than 1 inch and the maximum differential settlement was less than a half an inch.

SOLUTION AND RESULTS

Based on the sub-surface conditions and the design requirements, CNC Foundations and Helitech CCD chose Vibratory Stone Columns (VSCs or Geopiers) as the ground improvement method. We installed 24 inch diameter vibratory stone columns to a depth of 25 feet below the column and continuous footings.

In the floor slab area, CNC Foundations and Helitech CCD installed 24 inch diameter vibratory stone columns to a depth of 10 to 19 feet.

Overall, we installed 1,578 Vibratory Stone Columns to support the new foundation and floor slab.

CNC Foundations and Helitech CCD performed one (1) full scale modulus test and two (2) plate load tests to validate the design and installation of the VSC’s. The full scale load test had a quarter of an inch deflection at 1.5DL (17.55 kips). The two plate load tests had less than 0.14″ deflection at 1.0DL.

Project Details

SECTOR
Pharmaceutical Manufacturing Plant

LOCATION
Ohio

APPLICATION(S)
Deep Foundations, Vibratory Stone Columns (VSCs), Aggregate Piers

Not sure what geotechnical solution can work for your job? We can help.

Related Case Studies

Ball Park Village Phase 2 St Louis MO Vibratory Stone Columns

Ground Improvement

St. Louis Ballpark Village Site – Installing Vibratory Stone Columns

Ballpark Village St. Louis, Clark Avenue, St. Louis, MO, USA

View Case Study

Side overhead view of CNC team pouring concrete

Uplift Anchors

Vibratory Stone Column Uplift Anchor Installation at Western Carolina University

Cullowhee, NC

View Case Study

Controlled Modulus Columns vs. Vibratory Concrete Columns 3

Vibratory Concrete Columns

Pre-Drill VSCs and VCCs Fitness Center Chicago Suburb Oak Brook

OakBrook, IL

View Case Study

Let’s Talk

  • This field is for validation purposes and should be left unchanged.