PROJECT OVERVIEW

CNC Foundations was contracted with a ground improvement job for a new building addition at Rolling Hills High School. Following a thorough assessment by the engineers at CNC Foundations, it was determined that vibratory stone columns (VSCs) represented the most efficient solution for enhancing the site’s soil conditions to support the new building.

REQUIREMENTS AND CHALLENGES

This project presented no significant challenges. The entire endeavor was relatively seamless, adhering to the planned schedule and budget. There were no major obstacles impeding our crews’ access to the site, nor were there any safety-related procedures that could have potentially caused delays.

SOLUTION AND RESULTS

CNC Foundations, who strives to be your first choice in ground improvement, delivered a highly successful solution to Rolling Hills High School. At the end of the project the soil met the necessary building regulations and both the general contractor and Rolling Hills High School expressed complete satisfaction with the outcome.

Project Details

SECTOR
High School Building Addition

LOCATION
Byesville, Ohio

APPLICATION(S)
Vibratory Stone Columns (VSCs)

Not sure what geotechnical solution can work for your job? We can help.

Related Case Studies

Uplift Anchors

Cullowhee, NC | Aggregate Piers / VSCs & Uplift Anchors

Western Carolina University is one of the many universities that we have been fortunate to do ground improvement for throughout the U.S.

View Case Study

Ground Improvement

St. Louis, MO | Aggregate Piers / VSCs

CNC Foundations completed a project in St. Louis as an addition to Ballpark Village, an entertainment district adjacent to Busch Stadium.

View Case Study

Ground Improvement

Columbus, OH | Vibratory Stone & Concrete Columns

Three new buildings required a 7000 psf bearing pressure. CNC Foundations was selected to install an Aggregate Pier/VSC Ground Improvement.

View Case Study

Let’s Talk

  • By providing my phone number to CNC Foundations, I agree and acknowledge that CNC Foundations may send text messages to my wireless phone number for any purpose. Message and data rates may apply. We will only send one SMS as a reply to you, and you will be able to Opt-out by replying “STOP”. For more information on how your data will be handled please visit our Privacy Policy.