Chemical Storage Tanks

Installing Aggregate Piers

Ground Improvement – Installing Aggregate Piers

PROJECT OVERVIEW

Three UAN (Urea, Ammonia, and Nitrogen) Tanks, 176 feet in diameter, were being constructed in an agricultural area for a new Fertilizer Plant. Approximately 6,000 Aggregate Piers / VSCs were to be installed at the proposed site of the three tanks.

REQUIREMENTS AND CHALLENGES

The tanks were designed for a maximum settlement of 2 inches at the edge of the tanks. It was estimated that the total settlements on the order of 6 to 8 inches would occur if no ground improvement was performed. Aggregate Piers were to be installed through the upper soft soil stratum to the dense sands approximately 20 feet below subgrade to meet the project requirements.

Due to a very wet spring season, set preparation was delayed and put the project behind schedule. The project was two weeks behind when CNC Foundations was finally able to proceed with the installation of the Aggregate piers. To accommodate the General Contractor (GC) and get the project back on schedule, CNC Foundations added a VSC rig and crew to the site. This allowed us to make up the lost time and get the project back on schedule.

SOLUTION AND RESULTS

The entire project, in spite of the initial start date, was still completed two weeks prior to the original date committed to by the General Contractor.

Project Details

SECTOR
Large UAN Chemical Storage Tanks

LOCATION
Iowa

APPLICATION(S)
Aggregate Piers / Vibratory Stone Columns (VSCs) for Ground Improvement

Not sure what geotechnical solution can work for your job? We can help.

Related Case Studies

Ball Park Village Phase 2 St Louis MO Vibratory Stone Columns

Ground Improvement

St. Louis Ballpark Village Site – Installing Vibratory Stone Columns

Ballpark Village St. Louis, Clark Avenue, St. Louis, MO, USA

View Case Study

Ground Improvement

Chemical Formulating and Packing Facility

Installing Vibratory Stone Columns, Aggregate Piers, and Helical Piles

View Case Study

Controlled Modulus Columns vs. Vibratory Concrete Columns 3

Vibratory Concrete Columns

Pre-Drill VSCs and VCCs Fitness Center Chicago Suburb Oak Brook

OakBrook, IL

View Case Study

Related Case Studies

Vibratory Stone Columns

Pharmaceutical Manufacturing Plant

A chemical plant was adding a new manufacturing facility. We installed 1,578 VSCs to support the new foundation and floor slab.

View Case Study

Vibratory Stone Columns

Manufacturing Storage Facility

A company in Missouri added a new storage facility at their manufacturing site. This site is close to the Mississippi River and wetlands.

View Case Study

Vibratory Stone Columns

Oakley, CA | Aggregate Piers / VSCs & Liquefaction Mitigation

The location for the new logistics center in Oakley, CA was in an area prone to seismic hazards. We installed VSCs to help reduce the risk of liquefaction.

View Case Study

Let’s Talk