Healthcare Facility Case Study

This healthcare case study showcases our ability to adjust to changing client timelines and processes to deliver the ground improvement services they need.

Why Was CNC Foundations Needed?

PROJECT OVERVIEW

Our client, a healthcare facility in North Carolina, needed ground improvement services for their construction project. However, they ran into delays that changed the processes they needed from the project’s subcontractors, including us. Originally, the job was designed to occur in two site mobilization phases. These phases changed when the client did a peer review of the project designs and decided to add additional aggregate piers to it as a precautionary measure. Once the client made these changes, the site mobilization occurred in three phases. We did everything we could to adjust to the project changes.

REQUIREMENTS AND CHALLENGES

We installed the additional aggregate piers during the second mobilization. Inclement weather delayed the third mobilization, but as soon as it cleared, we completed the project on time and within budget. In the end, we installed 1,200 aggregate piers in the project’s foundation. We also installed 50 concrete and solid bar anchors for uplift. Our team showed the client that we can adapt to any changes they present and any inclement weather that pops up during site mobilizations.

SOLUTION AND RESULTS

The additional piers solidified the construction site’s soil and supported the client’s new structure properly. The client developed faith in our installation processes and was satisfied with our aggregate pier installations. After we completed this project, we began discussing future project opportunities with this client.

Project Details

SECTOR
Healthcare

LOCATION
North Carolina

SERVICE
Ground Improvement

APPLICATION(S)
Aggregate Piers

Related Case Studies

Ball Park Village Phase 2 St Louis MO Vibratory Stone Columns

Ground Improvement

St. Louis Ballpark Village Site – Installing Vibratory Stone Columns

Ballpark Village St. Louis, Clark Avenue, St. Louis, MO, USA

View Case Study

Side overhead view of CNC team pouring concrete

Uplift Anchors

Vibratory Stone Column Uplift Anchor Installation at Western Carolina University

Cullowhee, NC

View Case Study

Controlled Modulus Columns vs. Vibratory Concrete Columns 3

Vibratory Concrete Columns

Pre-Drill VSCs and VCCs Fitness Center Chicago Suburb Oak Brook

OakBrook, IL

View Case Study

Let’s Talk